Quick Take
-
Apply early: allow at least 3 months for small projects and at least 6 months for larger sites before move in or service date
-
Choose a build pathway: Lead in Conduit, Pit and Pipe, or Pathway
-
Submit designs, build to standard, lodge PCN and As Built, then nbn makes the site Ready for Service
-
Developers contribute under federal policy, and nbn is the default broadband provider but you can choose your carrier
-
Pre installing the nbn connection box at frame stage avoids delays and keeps handovers smooth
-
One Wire manages the entire process so builders and developers can focus on construction
Who Needs to Apply
You need to apply if you are creating new premises or addresses. This includes new dwellings, subdivisions, apartments and townhouses, and commercial lots or tenancies. Granny flats with their own address usually require an application. A single knock down rebuild typically does not unless it results in multiple new premises.
When to Apply
Small projects: apply at least 3 months before the required service date
Larger or multi stage projects: apply at least 6 months ahead
For smoother handover, book pre installation of the nbn connection box during frame stage or once the lead in trench is complete. Lodge the request at least 20 days before estimated completion.
💡 Tip from One Wire: We align your nbn timeline with your construction program so you avoid the delays that often catch builders out.
What You Will Need
Before you start, have these details ready:
Development address and application type
Total number of new nbn connections including services like fire panels or lift phones
Development details and site plans showing your chosen build pathway
Key contacts including ABN and billing information
Payment preference for developer charges
Multi stage projects start with one application then progress through the nbn New Developments Portal.
The Three Build Pathways
Lead in Conduit (LIC)
Best for small infill or single dwellings. You submit a service plan showing conduit routes.Pit and Pipe
For subdivisions, multiple stand alone dwellings, or new roads. Developers design and build pits and conduits to nbn standards, submit As Built and PCN, and nbn’s delivery partner completes the local network. One Wire also coordinates connection box pre installs at frame stage so residents are ready to connect on move in.Pathway (MDUs and complex builds)
Used for apartment blocks and vertical MDUs. Developers provide a master pathway plan and follow nbn standards through to PCC.
Step by Step: The nbn New Development Process
Plan early and choose your pathway with the right permits and designs
Submit the application with service or master plan
Accept terms and pay developer charges, then receive conditional approval (often used for council submissions)
Register for the New Developments Portal to track tasks, target dates, upload designs and later PCN and As Built
Design and build to nbn standards with One Wire ensuring compliance
Lodge Practical Completion Notice (PCN) and As Built via the portal; nbn inspects, and if compliant issues the Practical Completion Certificate (PCC)
Ready to Connect: nbn completes works to the boundary and residents can order services from their chosen provider
📌 One Wire Advantage: We manage each of these steps on your behalf. You get progress updates, not paperwork.
Charges and Responsibilities
Under the Telecommunications Infrastructure in New Developments policy, developers are responsible for fibre ready facilities and contributing to the cost of the network.
Developer contribution: per premises charge, capped by policy
Backhaul contribution: may apply if nbn backhaul is not nearby
End User Contribution: up to $300 per premises, usually recovered by the retail provider
Special cases include granny flats with their own address and knock down rebuild projects that create multiple dwellings.
Pre Installation: The Move In Day Accelerator
Booking a pre install of the nbn connection box during frame stage avoids delays for your clients. One Wire coordinates this step so residents can order a service on day one.
Council and Compliance in Victoria
Victorian councils often require confirmation that lots are connected or ready for connection as part of subdivision compliance. Fibre ready facilities are expected for all lots. One Wire provides the documentation councils need so your projects achieve timely sign off.
How One Wire Helps
Advises on the right pathway for your site
Prepares and submits applications and service plans
Manages the nbn New Developments Portal and tasks
Designs in line with current nbn standards
Coordinates trenching, conduit and pre installation of the connection box
Submits As Built and PCN, resolves remediation, and ensures PCC is issued
Provides clear handover packs for residents so they can order services quickly
Why Choose One Wire
Working with One Wire means you have a single point of contact who understands both the construction industry and nbn’s processes. We have managed hundreds of applications across Victoria and know the standards, common pitfalls, and council requirements. Our focus is making internet a feature, not a problem, by saving you time and delivering certainty.
✅ Ready to simplify your next project? Reach out to One Wire today and let us manage your nbn new development application so you can stay focused on construction.
For more detailed information and the latest updates, visit the official nbn website.
Disclaimer: The information in this article is based on guidelines published by nbn. One Wire provides this content as general guidance only and manages the application process on behalf of developers and builders. Final requirements, charges and approvals are determined by nbn.